Tank Jacks Tank Hydraulic Jacking System

Tank Jacks  Tank Hydraulic Jacking System

We are capable to provide full remedy for tank welding with different construction technique, equally bottom-to-leading and best-to-base tank development, hydraulic lifting program are specifically made for prime-to-base tank erection.

The following brief description offers the working treatment in outline. It can in specified specifics be modified when necessary.
 
Step one.  The tank base – plates are put on the prepared foundation and welded with each other.
Action 2.  The beams or lattice operate of the roof are assembled and lastly joined to the higher rim of the shell ring.
Step 3.  The jacking products is installed in the tank. The plates of the 2nd shell ring (following to the prime ring) are positioned exterior the initial a single.
Step4.   The concluded portion of the tank (roof and prime shell ring) is lifted hydraulically to a peak at which the plates of the second ring can be moved into area and the roof sheeting can be accomplished.
Step5.   The plates of the 2nd shell ring are found specifically and welded with each other to the reduced edge of the very first ring.
Step6.   The plates of the third shell ring are positioned outdoors the next shell ring.
Step7.   The concluded portion of the tank (roof the two uppermost shell rings) is lifted.
Step8.   The above cycle of functions is recurring until the last (base) shell ring is finished.
Step9.    The whole tank is reduced down to the base plate and welded to this.
Step10.  The lifting gear is dismantled.

Tank Jacks  Tank Hydraulic Jacking System